CONSERVATION COMMISSION MEETING
MONDAY, SEPTEMBER 19, 2016
7:00 PM
(Community Meeting Room)
7:00 PM (NOI-DEP #143-0912) PUBLIC HEARING: 117 Chestnut Street / ELLIS, KYLE
7:15 PM (NOI-DEP #143-0906) PUBLIC HEARING CONTINUED – 439 Northeast Main Street, 34 & 36 Davis Street / JMT SLEEPY HOLLOW, LLC & FITZPATRICK, JAMES
7:30 PM (NOI-DEP #143-0905) PUBLIC HEARING CONTINUED – 208 Yew Street /
GUARANTEED BUILDERS & DEVELOPERS
DISCUSSION
1. Request for a Certificate of Compliance: Dan Heney dba Orbison Corp, 16 Franklin Street (DEP #143-0904)
2. Tennessee Gas Pipeline: Matt Nowak
3. 42 Martin Road
4. Request for a Certificate of Compliance: Margaret Bacon, 80 Maple Street (DEP #143-0761)
5. MassDOT, Webster Street Project: Revised Plan
6. Request for Extension Permit for Order of Conditions: Jackson Song dba Cibao Developers, LLC, 209 South Street (Evergreen Estates)
7. Request for Project Review / Planning Board: Earth Removal Special Permit Application – JMT Sleepy Hollow, 439 Northeast Main and 34 & 36 Davis Streets (Phase 3)
8. Voucher (BSC Group)
9. Minutes: 8/15
10. Received a letter from the Burrillville Conservation Commission dated September 2, 2016 regarding a proposed power plant
Upcoming Meetings: 10/3, 10/17
Open session for topics not reasonably anticipated 48 hours in advance of meeting.